Tom’s Hardware reported on November 19, 2026, that the IEA’s World Energy Outlook 2026 projects 120 GW of additional global data-center capacity by the end of the decade, with 75% attributed to AI. Applying that share to the forecast addition implies 90 GW for AI (120 × 0.75). These figures measure capacity in gigawatts (GW); terawatt-hours (TWh) measure energy consumed over time. The forecast is global, not specific to the United States.

What the forecast says about AI data-center capacity

The outlook, as described by Tom’s Hardware, puts currently available capacity across all data-center types worldwide at 120 GW and anticipates another 120 GW by the end of the decade. The 90 GW AI figure is the arithmetic implication of the reported 75% share, not a separate reported measurement.

This adds a longer-term capacity measure to the question raised in NeoTeo’s earlier coverage of AI-slowdown calls and data-center expansion.

Capacity forecasts describe the scale of infrastructure; power generation and grid connections shape how that capacity can be served.

What the 50 GW projection covers

Tom’s Hardware also reported that the IEA tracks 93 large AI factories under construction or expansion using satellite imagery. Their combined capacity was reported to have risen from less than 2 GW to 17 GW over two years. The 50 GW figure is their projected combined capacity once those sites are complete, not their current capacity.

The 93-factory projection is a separate view of projects in development; it should not be added to the 120 GW global capacity forecast as though the figures covered distinct sets of facilities. The report does not provide a basis for treating them as separate totals.

Power sources and grid connections

The reported energy figures describe two different things: renewable sources account for nearly 50% of data-center power-purchase agreements, while coal and natural gas together provide closer to 60% of actual generation. Agreements describe contracted power; generation describes electricity produced.

Grid construction timelines are another constraint. Renewable power plants reportedly take one to five years to complete, while transmission projects can take three to five times as long. Tom’s Hardware describes grid connections as a bottleneck for data-center expansion.

How data-center growth could affect electricity bills

The IEA analysis, as quoted by Tom’s Hardware, found no clear relationship yet between growth in data-center capacity and electricity-price increases. The report describes different possible outcomes: costs could fall if facilities use existing capacity and pay their share, or rise if grid upgrades are needed and their costs are spread among customers. The effect therefore depends in part on local grid needs and how upgrade costs are allocated.