Zahl Limbuwala, DTCP’s director of operations, forecast that fewer than 20% of announced data center projects in Europe could be built over the next three or four years because of grid-connection constraints. The estimate concerns projects’ prospects for construction, not a count of completed facilities.
For a data center plan, grid access belongs alongside capacity targets from the start.
What does the European projects forecast say?
Limbuwala’s forecast centers on whether announced projects can secure a connection to the electricity grid. La Vanguardia reported his estimate and its stated cause: fewer than 20% of announced projects in Europe could be built within the forecast horizon because of connection constraints.
AWS public-policy representative David Blázquez also described the electricity grid as a decisive constraint on AI infrastructure, in his view, rather than capital or clean energy. A grid connection is the link that lets a facility draw electricity from the wider power system; its availability is therefore central to plans for operating data centers.
How do the EU capacity projections differ?
The reported project forecast is separate from projections about total EU data center capacity. La Vanguardia reported that the proposed EU Cloud and AI Development Act (CADA) aims to triple that capacity over five to seven years. It also attributed a projection of a doubling by 2030 to BloombergNEF and Ember. The two figures have different time horizons and describe separate projections.
What was debated about data centers in Spain?
La Vanguardia reported that participants cited land, international connectivity and renewable generation as advantages for Spain. It also reported that renewable sources generated 55.5% of the country’s electricity in 2025.
Begoña Villacis, executive director of Spain DC, criticized the wording of a proposed Spanish data center decree, arguing that it amounted to a prohibition. Her statement was an industry representative’s view of the draft.
What does the report propose cities address?
The DCD page for The Infrastructure of the AI Era describes a report covering grid access, water availability and permitting, alongside ten policy recommendations for cities preparing for AI infrastructure. La Vanguardia reported that the recommendations cover 2027–2030 and include administrative coordination, planning ahead for energy and infrastructure needs, and stable regulatory frameworks.