Spain’s Royal Decree 1032/2026 took effect on November 22, 2026. Ecologistas en Acción says the rules could make approval harder for three Amazon Data Services data centers in Huesca. The decree sets requirements for data centers in Spain; it does not itself decide the permits for those projects. Read the decree.

NeoTeo previously covered Spain’s draft framework for new data centers. The enacted decree sets a general grid-access threshold of 10 MW, compared with the 1 MW threshold in the draft.

Which data centers fall under the main rules?

The decree generally applies when a data center has at least 10 MW of grid-access power. Qualifying centers owned by the same company at the same location are counted together. A separate public-reporting requirement applies to facilities with at least 500 kW of IT power, regardless of their grid-access power.

RequirementThreshold or scopeRule and timing
General coverageAt least 10 MW of grid-access powerQualifying centers under the same owner at the same location are aggregated.
Public reportingAt least 500 kW of IT powerA separate reporting threshold, regardless of grid-access power.
High-category systemsSystems classified HIGH under Spain’s National Security FrameworkDigital-sovereignty rules apply regardless of grid-access power, after the data-center owner is notified of the classification.
Renewable additionality80% of total consumptionMust be covered by eligible renewable-generation or storage arrangements; the standard generation timing window is 36 months, subject to exceptions.
Hourly renewable matchingAt least 80% of electricity consumed in each hourEquivalent renewable electricity must be generated in that same hour; storage is allowed under the decree’s accounting rules.
Energy efficiencyTransitional PUE ceiling of 1.25Due after two years of operation, until the applicable European labeling system and methodology take effect.
Water efficiencyTransitional WUE ceiling of 0.1Due after one year of operation, until the applicable European labeling system and methodology take effect.

For systems classified HIGH, the decree generally requires content and service-derived data to remain within the EU or EEA. It also allows limited arrangements for technically indispensable remote operations. These rules are separate from the 10 MW threshold.

The two renewable requirements measure different things. Additionality concerns whether qualifying renewable arrangements cover a share of total consumption; hourly matching requires renewable electricity to correspond to consumption hour by hour. A yearly total alone does not meet the hourly test.

What are the efficiency and transition requirements?

The transitional PUE and WUE ceilings apply until the relevant European labeling system and efficiency methodology take effect. PUE is the decree’s energy-efficiency metric; WUE addresses water efficiency. Their compliance deadlines differ: two years of operation for energy efficiency and one year for water efficiency.

Eligible facilities can instead opt into a five-year SRAP route with staged hourly-matching levels. It requires 60% matching during P1 hours through December 31, 2028. From January 1, 2029, the levels rise to 70% for P1 hours and 60% for P2 hours through the transition period. Participating facilities must be technically able to reduce consumption to zero after the specified system signal; system-security measures can include disconnection for the strictly necessary period.

The decree also gives projects at different permit stages separate transition periods. Applications still being processed have three months to comply, while permitted projects that are not yet connected have six months to demonstrate compliance.

For a data-center proposal, grid-access power and permit stage are the practical starting points for understanding which requirements may apply.

What does the decree mean for the Huesca projects?

Ecologistas en Acción says the decree’s transparency, water-control and energy-efficiency requirements could make approval harder for three Amazon Data Services projects in Huesca. That is the organization’s assessment of the potential effect, not a permit decision.

The general threshold, aggregation rule and transition periods make project-specific details consequential: the decree treats facilities differently depending on grid-access power, ownership and location, and permit stage. Ecologistas en Acción’s warning identifies a possible approval hurdle; the decree supplies the rules that determine how individual projects are treated.