The EPA’s July 16, 2026 memorandum interprets the Acid Rain Program as not applying to power plants disconnected from the larger electricity grid. The agency says the memo does not make a final decision about any particular facility or constitute final agency action. Read the EPA memorandum.
For a data-center power project, its connection to the larger grid can change whether the Acid Rain Program applies.
What the EPA memo says about off-grid plants
The memo addresses “islanded” facilities: power plants with no connection to the larger electricity grid. Under the EPA’s interpretation of the program’s definitions, generation that serves a private consumer without connecting to that grid falls outside the Acid Rain Program’s requirements.
The EPA’s example describes a planned facility of about 500 megawatts, using natural-gas turbines and reciprocating engines to power an adjacent data center. It is an example in the memorandum, not a facility-specific decision.
What WIRED reported about Williams
In a report published November 23, 2026, WIRED said the EPA confirmed that Williams sought guidance about projects in Ohio and Utah and that meetings with the agency broadly addressed air regulations. WIRED associated the projects with Meta data centers; Williams’ submitted materials did not specifically mention Meta.
WIRED reported that Williams permitting director Steve Hall sent a letter to Utah’s environmental agency in February, and that the company filed an urgent meeting request in April concerning Ohio and Utah projects. The reporting does not establish that Williams’ outreach caused the EPA’s July interpretation.
What could change if a plant connects to the grid
The EPA says an off-grid facility that later connects to the larger grid may become subject to Acid Rain Program provisions. The memo advises developers to account for those permitting requirements in project planning.
The interpretation addresses the Acid Rain Program, not other provisions or programs under the Clean Air Act. It also leaves state permitting rules to the relevant authorities, whose requirements may vary.
Why monitoring remains part of the story
For plants covered by the Acid Rain Program, WIRED reported that permit applications are generally due two years before operation and that emissions are regularly monitored. The program’s applicability therefore affects permitting and emissions monitoring, while other air requirements may still apply under federal or state rules.
WIRED also reported that a Utah permit application for a Williams facility serving a Meta data center listed annual maximum emissions of about 100 tons of nitrogen oxide and 11 tons of sulfur dioxide. Those figures are permit maxima for that facility, not measurements of actual emissions.