On November 4, 2026, 24/7 Wall St. reported that TeraWulf had signed three credit-support agreements with Google for Anthropic leases at the Justified Data Campus in Hawesville, Kentucky. The reported support would take effect when the final data hall under each lease reaches its commencement date.
The leases cover three buildings and about 401 MW
The reported leases run for 20 years and cover three buildings with approximately 401 megawatts of capacity. TeraWulf CFO Patrick Fleury said the credit support strengthens the project’s financing profile and its ability to pursue competitive long-term debt.
Support is tied to each lease’s final data hall
The reported condition ties the support to the final data hall’s lease commencement, rather than to the signing of the agreements. The November 4 report said phased delivery was expected from late 2027 through the second quarter of 2028.
The $19 billion figure is for lease commitments
The approximately $19 billion figure describes the reported contracted lease commitments over the initial term. It is not a stated maximum for Google’s credit support.