A reported estimate attributed to Epoch AI puts Huawei’s Horinger data-center campus in Inner Mongolia at about 81,000 Nvidia H100-equivalents (H100e)—roughly 7% of Colossus 2’s estimated AI compute. H100e expresses compute against the Nvidia H100 as a reference; it is not a count of H100 GPUs installed at Horinger. The reported figures are estimates, not an audited chip inventory.
Treat H100-equivalents as a shared yardstick for comparing estimated compute, not as a tally of physical GPUs.
What the Horinger estimate says
The reported comparison puts Horinger at about 7% of Colossus 2 by estimated compute. Both figures are estimates expressed in H100-equivalents, so the comparison describes relative compute on that basis rather than the number of chips at either site.
The same account estimates Horinger’s inventory at about 105,000 Huawei Ascend 910C chips and 8,000 Ascend 910B chips. Those quantities are estimates, not a verified count of hardware in operation.
How the estimate was made
The method attributed to Epoch AI uses satellite-visible cooling equipment to estimate heat dissipation and power, then draws on Huawei chip sales and the lag between sale and deployment to estimate chip quantities. Substation and backup-generator figures serve as additional infrastructure checks.
The account associates 286 MW of estimated capacity with four buildings equipped for dense cooling. A November 2026 report described three of the four as operational. It also cites a 304 MW substation and 230 MW of backup generators. Those are separate infrastructure figures, not interchangeable readings of the 286 MW campus-capacity estimate.