FOX13 reported on November 22, 2026, that Memphis officials expected work on xAI’s South Memphis wastewater-recycling plant to resume in January. Its account described construction as paused. In June, WREG had reported that Mayor Paul Young said xAI committed to restarting by the first quarter of 2027. FOX13’s report and WREG’s account of the commitment describe separate points in the reported schedule.
Why construction was paused
In WREG’s April 2026 broadcast, Elon Musk said xAI was prioritizing the completion and stabilization of Colossus 2 before building the water-recycling plant. In June, MLGW president and CEO Doug McGowen said the project’s previous engineers were no longer employed and that a new engineering team had to be hired before work could resume. WREG’s broadcast includes the site report, footage of the October 2025 groundbreaking and statements from local officials and Sarah Houston of Protect Our Aquifer.
What the plant is designed to do
The planned facility would process treated wastewater into cooling water for xAI’s South Memphis computing operation, helping reduce its reliance on the Memphis Sand Aquifer. WREG reported planned processing capacity of up to 13 million gallons of wastewater per day. Sarah Houston separately described xAI’s MLGW contract as limiting its water use to up to 1.2 million gallons per day.
Planned processing capacity describes what the facility is designed to handle; a contract water-use limit describes how much water xAI may use.
Those figures refer to different measures: one is the plant’s planned wastewater-processing capacity, while the other is a contract limit on xAI’s water use. In its November account, FOX13 quoted Boxtown resident Ralph McKinney expressing concern about water reaching his home and urging xAI to follow through on its commitment.