Microsoft’s post-incident report says some delayed messages to consumer mailboxes that had been inactive for more than 30 days expired and generated non-delivery reports. Microsoft says all queued enterprise messages were delivered, with none found permanently lost. Active customer impact ended on November 13, 2026; the incident was formally declared resolved on November 14. Microsoft’s post-incident report attributes the outage to a failure in a specific gateway configuration used by Exchange Online.

What caused the Microsoft 365 outage?

Microsoft attributed the outage to a latent lock-contention defect in a Windows connection-processing process on the Microsoft 365 gateways used by Exchange Online. Under the incident’s load conditions, the contention exhausted CPU and memory. Microsoft said the defect was specific to that gateway configuration and did not affect standard Windows deployments.

Three conditions coincided with the defect: nearly 14% of gateway capacity was offline for routine operations, Microsoft Teams traffic failed over to gateways also supporting Exchange Online, and North American demand was nearing its daily peak. Automatic traffic redistribution spread the disruption. At the lowest point, more than 80% of North American gateway servers were unresponsive; Microsoft said failures reached every region within about two hours of the broad North American failures.

Microsoft’s lab load tests used older, lower-core hardware and different traffic conditions from those involved in the incident. The affected service hardware had more cores, which increased contention under the failure conditions.

When did customer impact end, and when was the incident resolved?

Microsoft recorded the incident start at 16:20 UTC on November 12. It said active customer impact ended at 16:10 UTC on November 13, while formal resolution came later, after extended monitoring.

MilestoneDate and time (UTC)What happened
Incident beganNovember 12, 16:20Microsoft recorded the start of the incident and a high-priority Exchange Online impact alert.
Active customer impact endedNovember 13, 16:10Microsoft said customers were no longer experiencing active impact; monitoring and recovery of the mail backlog continued.
Incident resolvedNovember 14, 04:15Microsoft declared the incident resolved after extended monitoring.

The distinction matters: the end of active disruption did not mark the end of Microsoft’s recovery work or monitoring.

Which services and emails were affected?

Exchange Online was the primary affected service. Microsoft also listed Microsoft 365 Copilot, Teams, SharePoint Online, OneDrive for Business, Defender, Purview, Fabric, Intune, Planner, Power Apps, To Do, Power BI, and Universal Print among services affected. The impact varied by service, region, connection method, and time; the list does not mean each service was fully unavailable.

For email, Microsoft extended the retry window from 24 to 48 hours. It said all queued enterprise messages were delivered and none were found permanently lost. Its detailed Exchange Online findings also say that some delayed messages for consumer mailboxes inactive for more than 30 days expired, and senders received non-delivery reports.

If you were expecting a message to a consumer mailbox inactive for more than 30 days, check for a non-delivery report; Microsoft says some delayed messages to those mailboxes expired.

What did Microsoft plan to change?

Microsoft said it had reverted the defective change, updated its Windows image, added capacity, and introduced temporary traffic guardrails. Its report also listed further engineering work, with different target timings.

For CY26 Q4, the report set targets for redesigning traffic distribution to prevent cascading failures, limiting Teams failover to the affected region, improving detection of capacity loss, and reducing notification delays.

For CY27 Q1, it set targets for gateway workload pools, Windows diagnostics and change auditing, fleet-wide recovery improvements, load testing on newer high-core hardware with representative traffic, and additional capacity. Other actions—including smaller fault zones, scoped failover testing, and gradual traffic ramp-up and admission control—were marked TBD.