The Senate and House held separate hearings on the VA’s Oracle electronic health record program on November 18 and 19, 2026. The reported $27 billion Oracle contract ceiling is distinct from the VA’s $56.5 billion long-term estimate. At the Senate hearing, the Government Accountability Office’s Carol Harris said GAO lacked the documentation to assess that estimate or verify the rollout schedule.
A contract ceiling covers one contract; a long-term program estimate can include years of deployment and upkeep.
How the $27 billion ceiling differs from the VA estimate
The $27 billion figure is Oracle’s reported contract ceiling. The $56.5 billion figure is the VA’s broader estimate, which includes costs beyond that contract. The VA reportedly increased Oracle’s ceiling by $17 billion in September, taking it from about $10 billion to $27 billion.
| Figure | Amount | Scope and period |
| Oracle contract ceiling | $27 billion | Reported ceiling after the increase in September |
| VA estimate | $56.5 billion | Broader long-term estimate |
| VA estimate component | $37.2 billion | Deployment, operation and improvement through 2031 |
| VA estimate component | $19.3 billion | A further decade of operation and maintenance |
The two VA estimate components add up to $56.5 billion. Harris said GAO could not assess the estimate from the documentation it had received, and she expected program costs to rise without being able to quantify the increase.
What scope figures lawmakers raised
At the November 18 Senate hearing, Senator Patty Murray cited an increase in veteran records from 8 million to more than 26 million between 2018 and 2026. She also cited increases of 129% in end users and 187% in system interfaces since 2018. Murray’s hearing account records those figures as part of her questioning of VA and Oracle officials.
Oracle co-CEO Mike Sicilia said the system had originally been expected to support 85,000 simultaneous users and was then expected to support 195,000. He also pointed to Oracle’s continuing responsibilities, including training. These were scope figures and explanations raised at the hearing; they do not assign a specific share of the cost increase to any one change.
Questions about veterans’ data, AI and safety tickets
At the November 19 House hearing, lawmakers questioned Oracle executives about commercial terms and possible AI use of veterans’ health data. Oracle executive Seema Verma said Oracle had no access to or use of that data. Sicilia said the next software version, including Oracle’s clinical AI agent, would be included for the VA at no additional cost.
Verma estimated that 1,000 to 1,800 patient-safety tickets were more than 90 days old. Representative Nancy Mace pressed her for an exact count.
Deployment progress and the schedule
The VA met its reported 2026 target of 13 deployments, bringing the system to 19 medical centers; the rollout plan covers 170 centers. VA official Neil Evans said the department had contracted for all 26 deployments planned for 2027, while prices for later work remained subject to negotiation.
The rollout was scheduled to finish in 2031. Harris said GAO could not verify that schedule from the records it had received.