SemiAnalysis estimated on September 25, 2026, that ByteDance accounts for roughly one-fifth of China’s delivered data-center capacity. The estimate describes ByteDance’s share of capacity, while SemiAnalysis says the company rents nearly all of its data-center footprint.

China’s capacity figures cover three different stages

SemiAnalysis’s model tracks more than 1,000 facilities operated by over 60 companies. It estimates China’s delivered data-center capacity at more than 24 gigawatts (GW), separately from about 20 GW in the dated pipeline and about 30 GW in announced projects.

Capacity stageEstimateWhat it describes
Delivered capacityMore than 24 GWCapacity already delivered
Dated pipelineAbout 20 GWCapacity in the dated project pipeline
Announced projectsAbout 30 GWAnnounced data-center projects

ByteDance rents nearly all its data-center footprint

SemiAnalysis describes ByteDance as China’s largest data-center tenant and says the company rents nearly all its footprint. It also identifies self-build clusters in Datong, Shanxi; Wuhu, Anhui; and Horinger and Ulanqab in Inner Mongolia.