Bloomberg reported that Saturn Funding Trust sold $32 billion in bonds on November 19 in a financing tied to SpaceX’s Nvidia-chip equipment. On October 24, SpaceX entered a binding commitment letter to enter a master finance lease, estimating about $40 billion in aggregate principal payments. A separate report says lenders requested an Earth-only clause for Nvidia Vera Rubin NVL72 systems; whether it entered the final agreement was unclear.
What the $32 billion and $40 billion figures measure
The $32 billion is the bond sale Bloomberg reported for Saturn Funding Trust. The approximately $40 billion is SpaceX’s estimate of aggregate principal payments under the contemplated lease. They describe different parts of the financing. Bloomberg reported the bond sale; SpaceX’s SEC filing gives its lease-principal estimate.
The $40 billion is principal, not the full sum of lease payments: the contemplated rent also includes a fixed-rate charge and certain ongoing costs and expenses. For broader coverage of money and investing alongside this corporate-financing story, NTV88 is a related publication.
Keep the bond-sale amount and the lease-principal estimate separate; the lease’s payment formula also includes a rate charge and ongoing expenses.
How SpaceX described the lease payments
SpaceX’s commitment letter concerned a master finance lease with an Apollo-managed entity. The equipment would include GPU pods and related equipment for data centers SpaceX selected. Each lease schedule was expected to run about five to five-and-a-quarter years from its start date.
Rent was to be paid quarterly in advance. The contemplated formula includes one-twentieth of a tranche’s financed cost, a charge at a fixed annual rate on the outstanding lease balance, and specified ongoing costs and expenses. The fixed rate was to be set during pricing before the master lease was entered. SpaceX’s filing said closing was expected before the end of 2026, subject to conditions, with lease schedules expected to begin in the first half of 2027 as GPUs were delivered.
NeoTeo previously covered earlier reported chip-financing discussions involving SpaceX, Broadcom and Oracle; SpaceX’s filing set out the commitment and payment mechanics for this lease.
What lenders reportedly requested about the chips
Yahoo Finance, relaying a Financial Times report, said lenders requested that financed Nvidia Vera Rubin NVL72 systems remain on Earth so they could be recovered in the event of a default. The report said it was unclear whether the requested restriction made it into the final agreement. Yahoo Finance’s account describes the request and its reported status.