On November 16, 2026, André Thierig, head of Tesla’s Gigafactory Berlin-Brandenburg, said the company planned to invest about €3 billion in a new production building at Grünheide, near Berlin, and had already begun hiring for construction and manufacturing planning. He said construction was expected to start in the first half of 2027, with Cybercab production planned for 2029. Thierig’s announcement
The announced sequence starts with recruitment, then targets construction in 2027 and Cybercab production in 2029.
What Tesla said was already underway
In his post, Thierig said Tesla was recruiting for the Grünheide project, particularly for construction and manufacturing-planning roles. That puts hiring among the preparations underway before the planned start of building work.
For more on the vehicle’s driverless design, read NeoTeo’s earlier Cybercab investigation.
The planned factory schedule
Thierig set the expected construction start for the first half of 2027 and the planned start of Cybercab production for 2029. He also said Tesla intended eventually to ramp Cybercab output to as many as one million vehicles per year.