On November 16, 2026, André Thierig, Tesla’s senior director at Giga Berlin, announced a first investment of around €3 billion in a new manufacturing building at Grünheide, Germany. His post said Cybercab production there was anticipated in 2029. Thierig’s announcement sets out a plan for the site.

How large is the reported Cybercab capacity?

Quartz reported an eventual capacity ambition of up to one million Cybercabs a year for the proposed building. That figure describes planned capacity, not how many vehicles the factory will produce in a given year. Thierig described the roughly €3 billion as a first investment in the new building.

A factory’s capacity is its planned production ceiling; annual output is what the line builds in a particular year.

What milestones are reported for the project?

The reported schedule runs from a permit application through construction to the anticipated production start:

TimingProject milestone
November 16, 2026Thierig announced the first investment and anticipated production at Giga Berlin.
Before the end of 2026Tesla was reportedly planning to submit a building-permit application.
First half of 2027Construction was reported as expected to begin.
2029Cybercab production was anticipated at Giga Berlin, according to Thierig.

The German factory project is separate from Tesla’s reported Cybertruck production-line plans in Texas, covered in NeoTeo’s earlier report.

What early work and staffing are reported?

Thierig also said Tesla was hiring for the project. Quartz reported that the company was seeking a few hundred people for early construction and manufacturing-planning work. Notebookcheck reported that the proposed expansion also includes supporting buildings and a second wastewater-treatment facility.

Quartz, relaying AFP, reported that Brandenburg head Dietmar Woidke welcomed the investment for its economic significance. IG Metall regional leader Jan Otto welcomed its potential employment effects.