Texas A&M’s Semiconductor Institute is a university project at the RELLIS campus in Bryan, separate from the Terafab manufacturing complex planned for Grimes County. At a November 16, 2026, briefing, Texas A&M System leaders said the institute building was about 20% complete. Its director, Steve Putna, described practical student training as a way to prepare for potential Terafab jobs.
What the institute plans to do
A presentation to the Brazos Valley Intergovernmental Committee described an industry-style cleanroom with six laboratories. Putna said the institute is meant to give students practical experience relevant to semiconductor work, including potential roles at Terafab.
The training facility and Terafab have different locations and purposes: the institute is at RELLIS in Bryan, while Terafab is a planned manufacturing complex in Grimes County. The institute’s workforce role is part of Texas A&M’s stated plan for practical training.
The construction estimates cover different scopes
KBTX reported that the Texas A&M System put the broader RELLIS project at $205.5 million, including the institute building, a water tower and a water well. A Texas Department of Licensing and Regulation project record lists a separate estimated cost of $144.9 million for new institute construction and associated sitework.
The $144.9 million estimate covers registered construction and sitework; the $205.5 million figure includes water infrastructure in the wider project.
The institute’s planned schedule
Putna told KBTX that substantial building completion was expected by the end of 2027, with equipment installation afterward and significant operations planned for mid-2028. The TDLR record lists January 13, 2028, as the scheduled completion date for the registered construction project.
Terafab has a separate production target
eeNews Europe reported that Elon Musk described the third or fourth quarter of 2028 as Terafab’s production target during a SpaceX earnings call on October 20, 2026. The publication characterized that schedule as ambitious and uncertain. NeoTeo’s earlier coverage of Musk’s reported Terafab timetable covers that production target.