TSMC filed an application on November 23, 2026, describing a proposed semiconductor campus in Brazos County, Texas. The filing outlines one or more fabs for 2nm and more advanced logic chips, but says nonbinding land agreements do not commit TSMC to buy the property or make a final site selection. The Texas Comptroller application places the proposal within a site-selection process.

What the application proposes

The proposed campus would occupy a 3,231.813-acre site in Brazos County, within College Station Independent School District. The application describes one or more front-end semiconductor fabrication facilities, along with supporting infrastructure. The proposed fabs would make logic chips using 2nm and/or more advanced process technologies for markets including AI, high-performance computing and mobile applications.

What the requested JETI limitation covers

The application seeks a property-tax limitation through Texas’s Jobs, Energy, Technology and Innovation (JETI) program. TSMC Arizona Corporation, named in the packet’s economic-benefit statement, says recurring property taxes affect the project’s financial model and calls the limitation a determinative factor in whether the investment can be economically justified in Texas.

The application’s description of eligible property excludes land and land-acquisition costs, inventory, and property already on the land before a JETI agreement. The applicant’s rationale ties the requested limitation to its Texas site decision.

A tax limitation can shape where a fab is built; in this filing, the applicant makes it part of the Texas site decision.

What the economic analysis projects

The application’s economic-benefit analysis projects $22,619,235,774 in total investment and 2,099 permanent workers at full operations. Its other estimates cover distinct parts of the proposed project:

MeasureApplication estimateScope
Total investment$22,619,235,774Projected total
Buildings and other real-property improvements$8.60 billionProjected investment category
Machinery and equipment$14.02 billionProjected investment category
Construction costs$5,586,951,236Estimated construction costs
Permanent workers2,099Projected workforce at full operations

The investment categories are rounded estimates; construction costs are a separate estimate, not an additional investment category. The worker figure describes the projected workforce at full operations, not current employment.

The proposed fab has two reported schedule milestones

The application’s analysis models construction from 2027 through 2031 and labels 2032 as the year of full operations. Separately, Data Center Dynamics reported a 2029 operational target. The filing’s full-operations year and the reported operational target are distinct schedule descriptions.