Brazos County says TSMC is evaluating a proposed $22.6 billion semiconductor fab in Precinct 1. The facility would make advanced logic chips using 2-nanometer-or-more-advanced technology for AI, high-performance computing and mobile applications. The county says the project is a chip factory, not a data center, and that required approvals and TSMC’s final investment decision are still pending. Brazos County’s project description

What TSMC is proposing for Brazos County

A semiconductor fab makes chips; this proposal covers one fab, rather than a data center. The county’s summary describes the intended chips and process technology, and puts the proposed investment at $22.6 billion.

The proposal is in Precinct 1, within College Station’s extraterritorial jurisdiction and College Station ISD boundaries. KBTX reported on Nov. 25 that the proposed site covers just over 3,200 acres, the land was under contract rather than purchased, and Arizona remained an alternative.

What the job and economic figures cover

Brazos County’s summary projects at least 2,099 direct jobs with an average annual salary of $133,000. Those figures refer to jobs at the proposed facility.

A separate Greater Brazos Partnership analysis, described by KBTX, projects 7,160 countywide jobs at a peak in 2033 and $1.7 billion in annual economic output from one fab. The analysis also projects about $1.4 billion in new state revenue over 10 years. These countywide and state figures have a broader scope than the facility’s projected direct employment.

The direct-job estimate and the countywide job projection describe different scales of impact: one counts jobs at the fab, the other projects jobs across the county.

KBTX also reported projections attributed to the Texas Comptroller of a $354 million school property-tax break and about $405 million in school operating taxes over 20 years. The state would replace revenue College Station ISD loses. Both figures are projections, not realized tax results.

What local utility forecasts say

Tom Johnson, president of the Greater Brazos Partnership, forecast that water would be brought in from outside the region and that the facility would eventually reclaim more than 90% of its water. He also forecast that added electric capacity and commercial customers paying part of system costs could lower residential electricity rates. These are Johnson’s forecasts about possible local effects.

What College Station ISD lists next

The College Station ISD board page lists a Dec. 10, 2026 public hearing and links separate notices for the JETI application and the proposed TSMC Reinvestment Zone #1. The district’s board meeting page KBTX reported Dec. 24, 2026, as Texas Gov. Greg Abbott’s deadline to decide on the JETI application.