WIRED reported on November 23, 2026, that Williams sought EPA guidance for power projects in Ohio and Utah, and that the agency confirmed the request. In July 2026, the EPA recommended that certain power plants serving data centers exclusively be exempt from the Acid Rain Program. WIRED’s report details the requests; the EPA’s July guidance describes the recommendation.
Williams, a natural-gas power provider for several Meta data centers, sought guidance about projects in Ohio and Utah. For separate context on Meta’s climate goals, NeoTeo previously covered the company’s reported reassessment of its 2030 net-zero goal.
The key distinction in the EPA’s recommendation is whether a plant serves data centers exclusively or sells electricity to the public grid.
What the EPA recommended
The EPA’s guidance addresses certain “islanded” power plants: facilities that supply data centers exclusively rather than sell electricity to the public grid. Its recommendation concerns that specific category of plant.
How Williams pressed the issue
Williams had publicly advocated an exemption in testimony to the U.S. House of Representatives in September 2025, according to WIRED. In a letter to Utah regulators dated February, Williams permitting director Steve Hall argued that plants serving data centers alone were not subject to the program because they did not sell power to the public grid. The EPA confirmed to WIRED that Williams sent the letter.
In April 2026, Williams requested meetings about its Ohio and Utah projects and described the discussions as urgent. EPA calendar records reviewed by WIRED showed that Williams executives were invited to at least two meetings with agency officials, including at least one with Aaron Szabo, then chief of the EPA’s Air Office. The agency told WIRED that the meetings broadly concerned air regulations and that Williams sought guidance on both projects.
The EPA’s July recommendation followed those requests in the same broader debate over how the program applies to power plants dedicated to data centers. The documented sequence does not, by itself, establish that the meetings caused the guidance.
What emissions reporting is at stake
For plants covered by the Acid Rain Program, WIRED says permit applications must be submitted two years before a facility comes online and emissions must be monitored regularly. The reporting at issue includes sulfur dioxide, nitrogen oxides and carbon dioxide.
Joseph Goffman, a former assistant administrator at the EPA’s Office of Air and Radiation, said an exemption could reduce the emissions information regulators receive, including information about carbon dioxide. That is a potential oversight consequence, not a reported outcome.
The debate over the program’s scope
Williams argued that the program was not intended for plants that do not sell electricity to the public grid. Carrie Jenks, director of Harvard Law School’s Environmental and Energy Law Program, and Goffman said the EPA’s interpretation appeared consistent with the program’s original scope. Earthjustice and the Natural Resources Defense Council challenged the agency’s interpretation in a letter to the EPA in September 2026.
The EPA told WIRED that its program offices regularly meet with stakeholders in their areas of jurisdiction. Williams spokesperson Alex Schott said the company was committed to developing energy solutions for AI while prioritizing environmental protection and modernizing construction and implementation timelines.