A November 18 report said United Launch Alliance (ULA)’s preliminary review linked the Vulcan rocket’s low first-stage thrust to inadequate fuel supply from the vehicle to its BE-4 engines. Vulcan failed to deliver 40 Amazon Leo satellites to orbit on November 15; the reported finding did not identify a failed component or final cause.
When did Vulcan’s performance fall short?
ULA’s early account placed the first-stage performance shortfall shortly after liftoff. The stages separated too low and below the velocity needed to reach orbit, and telemetry was lost about 10 minutes into the flight. The loss of telemetry came later in the sequence than the start of the underperformance. ULA’s update covers the flight sequence and investigation oversight. NeoTeo’s earlier account of the Vulcan flight provides more context on the initial sequence.
The fuel-supply finding points to a suspected link between the vehicle and its engines; it does not name the part responsible.
What did ULA’s preliminary finding say?
The reported explanation focused on fuel reaching the two BE-4 engines, rather than on engine performance. ULA’s statements about other parts of the rocket were also preliminary: it said the Centaur upper stage and its RL10 engines operated as planned but could not recover the first-stage performance loss. ULA also said the flight’s six solid rocket boosters performed nominally after nozzle improvements.
Who is investigating the failure?
ULA is leading the investigation. The Federal Aviation Administration (FAA) oversees it, participates throughout, and approves the final report and corrective actions. A November 18 account said no return-to-flight date had been announced at that point.
Reports put Blue Origin’s New Glenn return target in January 2027