At the November 3, 2026, PIC Summit in Eindhoven, speakers called for Europe to move chip and photonics projects beyond pilot lines and into production, I+O reported. The Netherlands’ Permanent Representation to the EU said construction of PIXEurope’s photonic-chip pilot line began March 9, 2026, at High Tech Campus Eindhoven.
Europe’s chip scale-up challenge
A pilot line can advance a chip process, but the summit discussion focused on the harder step between pilot work and production at industrial scale. I+O reported that Werner Steinhögl, a European Commission sector head for microelectronics and photonics, described an intermediate phase between a pilot line reaching technological maturity and building a factory.
Integrated photonics uses light to transmit data on a chip. At the summit, NXP CTO Lars Reger pointed to an internal company benchmark of selling 500 million units of one chip to illustrate the scale associated with production. That figure was NXP’s own benchmark, not a general industry threshold.
PIXEurope’s pilot-line construction
The Netherlands’ Permanent Representation to the EU said the Netherlands was investing €172 million in PIXEurope’s photonic-chip pilot production line. The project’s announced milestone is construction of a pilot line at High Tech Campus Eindhoven.
Permitting, grid capacity, and demand
I+O reported Peter Wennink’s account of a planned AI gigafactory in Rotterdam’s port area. Wennink said a customer had committed to one-third of the planned capacity, while prospective power from North Sea wind faced grid-capacity constraints and the project was held up by permits at the time of his remarks. The example puts permitting and electricity access alongside customer demand as factors in moving a large industrial project forward.
I+O also reported two distinct positions on permits for new chip factories: the European Commission had proposed a maximum period of 12 months, while European Parliament member Bart Groothuis advocated a six-month target.